Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the remove-replace-gf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /www/wwwroot/old.huanqikj.cn/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the image-optimization domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /www/wwwroot/old.huanqikj.cn/wp-includes/functions.php on line 6121
组件层压工艺 - 深圳太阳能板厂家/工厂,专注太阳能板生产15年-幻启科技(深圳)有限公司
您现在的位置:

组件层压工艺

幻启太阳能科技 11/09/2020

组件固化工艺

将敷设好的电池放入层压机内,通过抽真空将组件内的空气抽出,然后加热使EVA熔化将电池、玻璃和背板粘接在一起;最后冷却取出组件。层压工艺是组件生产的关键一步,层压温度层压时间根据EVA的性质决定。我们使用快速固化EVA时,层压循环时间约为22分钟。固化温度为145℃ 左右。

太阳能组件层压
太阳能组件层压

层压工艺要求:对于不同的EVA,层压的工艺有所不同,这里以国产EVA和日棉EVA为例来进行层压工艺的说明。

国产EVA

太阳能组件层压
太阳能组件层压

日棉EVA

太阳能组件层压
太阳能组件层压